News Story

Print
Press Enter to show all options, press Tab go to next option

Media inquiries: For photos and other media resources, please contact the Public Information Office at 360.383.3310 or pio@whatcom.ctc.edu. Thanks for your interest!

 

Campus improvement projects beginning this summer

Post Date:05/25/2017 9:14 a.m.

As summer rapidly approaches, WCC's Facilities and Operations staff are preparing for several repair, remodels, and improvement projects on campus, which will begin in June. In addition to those projects, WCC’s next major capital project, the Phyllis & Charles Self Learning Commons (LRN) is scheduled to break ground this summer. Below is a summary of some of the work we hope to accomplish on campus over the next few months and some potential operational impacts. Also included is information on the Learning Commons, which will carry construction activities through summer 2019.

Please take a moment to review the project list and consider the potential operational impacts listed for each. As always, Facilities and Operations staff will do their very best to limit disruption to campus. Please pay particularly close attention to construction signage and messaging regarding safety in construction areas. We ask for your patience and understanding as we all work together to complete these exciting improvements to campus.

 

Phyllis & Charles Self Learning Commons (LRN) – The Learning Commons will be the first state-funded major construction project on our campus since Kulshan Hall was completed in 2005. The new 65,000 sq. ft. facility will integrate the full resources of the library with academic support services, including the learning, math and writing centers and tutoring services. It  will also provide access to instructional technology, collaborative workstations, and individual and group study spaces. The co-location of functions will provide for future flexibility, spark collaboration, and provide students with access to a variety of resources to support their unique learning needs. For more information on the Learning Commons visit whatcom.edu/learningcommons.

  • Construction Schedule: August 2017 - July 2019
  • Design Consultant: Schreiber Starling & Whitehead Architects
  • Work to be performed by: Contractor not yet selected

Operational Impacts:

  • Noise related to major earthwork, and construction activity.
  • Construction traffic entering and exiting campus from Kellogg Rd. and Stuart Rd.
  • Occasional dust from earthwork and construction traffic.
  • Temporary lane closures on Kellogg Rd.
  • Construction equipment and material staging in the grass lawn area east of Kulshan Hall.
  • Construction fencing will prevent access to Kulshan field once construction starts.

 

Cascade Emergency Generator System – A new 150kW natural gas powered generator will be installed on the west side of Cascade Hall near the existing power transformer. In addition, a new uninterrupted power system (UPS) will be installed to provide constant power to the data server room. The new system will allow the college to maintain our data and phone servers through an extended power outage and greatly reduce ongoing issues created when the servers are forced to be shut down and restarted. 

  • Construction Schedule: June - August 2017
  • Design Consultant: Zervas Group Architects and K-Engineers
  • Work to be performed by: Veca Electric Inc.

Operational Impacts:

  • Sections of walkways and parking spaces immediately adjacent to Cascade may be temporarily closed as work progresses. Alternative, accessible routes will be identified to maintain building access.
  • Noise related to demolition and construction activity may be noticeable inside the building.
  • There may be scheduled phone and data outages as the server room equipment is migrated to the new generator and back-up power system. Outages will be scheduled to limit disruption to campus and will be communicated in advance.

 

Kulshan Room 108 Lab Conversion – This project will convert Kulshan 108 to a hybrid lab to be utilized by both chemistry and biology classes. The project consists of light demolition, plumbing, electrical, and mechanical work. New cabinets, countertops and student work islands will be installed along with new fume hoods and other laboratory equipment.

  • Construction Schedule: June - October 2017
  • Design Consultant: RMC Architects
  • Work to be performed by: Roosendaal Honcoop Construction

Operational Impacts:

  • Noise related to demolition, framing, sheet rock, and other trades work.
  • Occasional smell of hot works associated with brazing/welding of plumbing and duct work.
  • Possible disruption to service drive area on west side of Kulshan and the interior hallways during equipment and material deliveries.
  • Construction activities will likely carry into the fall quarter 2017.

 

Kellogg Road Crosswalk Safety Improvements – Additional lighting, signage, and signalization will be added to the Kellogg Rd. crosswalks between Laidlaw Center/Kulshan Hall and Pavilion/Cascade Hall. This is the first phase of a multi-project initiative to improve awareness and pedestrian safety on campus.

  • Construction Schedule: June – September 2017
  • Design Consultant: Zervas Group Architects, K-Engineers, Wilson Engineering
  • Work to be performed by: Contractor not yet selected

Operational Impacts:

  • Dust and noise related from the operation of excavators, jackhammers, and other construction equipment along Kellogg Road.
  • Traffic delays and periodic lane closures on Kellogg Road throughout construction.
  • Construction equipment and material staging in the service drive west of Laidlaw.
  • Temporary closure of sidewalk areas and crosswalks along Kellogg Road throughout construction.

 

Pavilion Gymnasium Exhaust Fan Replacement – The old exhaust fans serving the Pavilion gym will be removed and replaced with new units. New roofing will also be installed in the mechanical area on the south side of the gym.

  • Construction Schedule: June - July 2017
  • Design Consultant: Zervas Group Architects and Sazan Group
  • Work to be performed by: Hytech Roofing Inc. and Andgar Corporation

Operational Impacts: 

  • Noise related to the demolition and construction activity.
  • Temporary interruption to ventilation system for the gym.
  • Several parking spaces south of the Pavilion will be reserved for material staging and contractor parking.
  • Work will be coordinated to limit disruption to Commencement activities.

 

Baker 115 & 117 Computer Lab Upgrades – The mediated business lab currently in BKR 117 will move to BKR 115. Baker 117 will undergo a light remodel to accommodate a new computer information systems/computer science  lab. Work involves the installation of new power and data, new anti-static flooring, new furniture, and new technology (i.e. computers, audio/visual equipment, etc.). The mediated business lab (BKR 115) will be ready for summer quarter 2017, the new CIS/CS lab (BKR 117) will be completed by fall quarter.

  • Construction Schedule: May - July 2016
  • Design Consultant: K-Engineers
  • Work to be performed by: WCC Computing Resources and Maintenance Staff

Operational Impacts: 

  • Noise related to the demolition and construction activity.
  • Occasional smell associated with painting and flooring adhesive.
Return to previous list >>

 

Sign up to receive news from Whatcom Community College to your email